Safety Package Formal Review Report#

Persistency Safety Package Formal Review
status: valid
security: NO
safety: ASIL_B
tags: persistency
realizes: wp__fdr_reports

1. Purpose

The purpose of this review checklist is to report status of the formal review for the safety package.

2. Checklist

Table 50 Safety Package Checklist#

Id

Safety package activity

Compliant to ISO 26262?

Comment

1

Is a safety package provided which matches the safety plan (i.e. all planned workproducts referenced)?

[YES | NO ]

<Rationale for result>

2

Is the argument how functional safety is achieved, provided in the safety package, plausible and sufficient?

NO

The argument is intentionally not provided by S-CORE.

3

Are the referenced work products available?

[YES | NO ]

<Rationale for result>

4

Are the referenced work products in released state, including the process safety audit?

[YES | NO ]

<Rationale for result>

5

If safety related deviations from the process or safety concept are documented, are these argued understandably?

[YES | NO ]

<Rationale for result>