Startup & Shutdown#
The sequence diagrams below are based on the example dependency graph.
Launch Manager initial startup#
The Initial Run Target configuration is shown in Configuration Structure.
Launch Manager Startup
|
status: valid_inspected
security: YES
safety: ASIL_B
|
||||
In case of initialization failure, the Launch Manager fails to start. Once initialization is successful, the Launch Manager activates the configured initial Run Target. For the detailed Run Target activation sequence, refer to Run Target activation. |
|||||
Launch Manager shutdown#
Launch Manager Shutdown
|
status: valid_inspected
security: YES
safety: ASIL_B
|
||||
When the Launch Manager receives a SIGTERM signal, it will initiate transition to Run Target Off which leads to termination of all components. Afterwards, the Launch Manager process itself exits. For the detailed Run Target activation sequence, refer to Run Target activation. |
|||||