Release Gate v0.9 — 14 July – 7 September 2026#

Milestone: score/v0.9

Focus: Implementation (PA4)

  • A Module Verification Report must be extended for every module, showing at least 75% component requirement test coverage (linked via FullyVerifies / PartiallyVerifies on comp_req__... IDs in unit tests and component integration tests)

  • A Platform Verification Report must be created, showing at least 75% feature requirement test coverage (linked via FullyVerifies / PartiallyVerifies on feat_req__... IDs in Feature Integration Tests)

  • Detailed design documented for all modules (no open TBDs, status valid)

  • Fill in and approve chklst_impl_inspection.rst for all modules — each checklist point is either completed or the finding is noted in the checklist with a tracked issue

  • Remaining requirements (the ~20%) must have tracked tickets in the main S-CORE GitHub project — each ticket must have the component set and the milestone set

Current State

See the relevant tables in Overall Status: