Safety Plan Formal Review Report#

Persistency Safety Plan Formal Review
status: valid
security: NO
safety: ASIL_B
tags: persistency
realizes: wp__fdr_reports

Purpose

The purpose of this safety plan formal review checklist is to report status of the review for the safety plan.

Conduct As described in wf__p_formal_rv, the formal document review is performed by an “external” safety manager:

  • reviewer: <committer with safety manager skills explicitly named here>

Checklist

See also doc_concept__wp_inspections for further information about reviews in general and inspection in particular.

Table 6 Safety Plan Checklist#

Id

Safety plan activity

Compliant to ISO 26262?

Reference

Comment

1

Is the rationale for the safety work products tailoring included?

[YES | NO ]

std_req__iso26262__management_6451 std_req__iso26262__management_6455 std_req__iso26262__management_6457 std_req__iso26262__management_6467

<Rationale for result>

2

Is impact analysis planned in case of re-use of SW (needed for every release following the first formal release)?

[YES | NO ]

std_req__iso26262__management_6452

<Rationale for result>

3

Does the safety plan define all needed activities for safety management (incl. formal document review and Safety Audit)?

[YES | NO ]

std_req__iso26262__management_6465 std_req__iso26262__management_6491 std_req__iso26262__management_64111

<Rationale for result>

4

Does the safety plan define all needed activities for System and SW development, integration and verification?

[YES | NO ]

std_req__iso26262__management_6465

<Rationale for result>

5

Does the safety plan define all needed activities for safety analysis and DFA?

[YES | NO ]

std_req__iso26262__management_6465

<Rationale for result>

6

Does the safety plan define all needed activities for supporting processes (incl. tool mgt)?

[YES | NO ]

std_req__iso26262__management_6465

<Rationale for result>

7

Does the safety plan document a responsible for all activities?

[YES | NO ]

std_req__iso26262__management_6463

<Rationale for result>

8

If OSS software components is used, is it planned to be qualified?

[YES | NO ]

std_req__iso26262__management_6455

<Rationale for result>

9

Is a safety manager and a project manager appointed for the project?

[YES | NO ]

std_req__iso26262__management_6461 std_req__iso26262__management_6462

<Rationale for result>

10

Is safety plan sufficiently linked to the project plan?

[YES | NO ]

std_req__iso26262__management_6464

<Rationale for result>

11

Is safety plan updated iteratively to show the progress?

[YES | NO ]

std_req__iso26262__management_6468

<Rationale for result>